DC/25/05579 decided approve
Last updated 15/04/2026, 15:16
Application for approval of details reserved by Requirement 22 under The Progress Power (Gas Fired Power Station) Order 2015.
Discharge of Requirement
Full Proposal
Approval of Details reserved by Requirement 22 pursuant The Progress Power (Gas Fired Power Station) Order 2015
Application Timeline
- Application Registered
- 17/12/2025
- Application Validated
- 17/12/2025
- Target Decision Date
- 24/12/2025
- Committee Date
- N/A
- Decision Made
- 15/04/2026
- Decision Issued
- 15/04/2026
Case Officer
Applicant
Jesper Howe