Notification of pre-commencement operations for archaeological investigations under Schedule 3, Requirement 3(1). The operations are scheduled from May 5, 2026, to October 30, 2026.
Discharge of Requirement
Bramford, Ipswich
Full Proposal
Notice of pre-commencement operations under Schedule 3, Requirement 3(1) Stages of the authorised development: Notification of Pre commencement Operation -Archaeological investigations . Requirement 3-(1) - The anticipated programme for these pre-commencement operations is from Tuesday 05/05/26 - Friday 30/10/26.
Application Timeline
- Application Registered
- 27/04/2026
- Application Validated
- 27/04/2026
- Target Decision Date
- 04/05/2026
- Committee Date
- N/A
- Decision Made
- 30/04/2026
- Decision Issued
- 30/04/2026